Saint John Water 2018 Capital Budget 11-Sep-17 THE CITY OF SAINT JOHN SAINT JOHN WATER CAPITAL PROGRAM SUMMARY W & S UTILITY FUND Proposed Program Summary For - 2018 No. ofOtherUtility Category Total ProjectsShareShare Infrastructure Renewal - Sanitary12$600,000$2,075,000$2,675,000 Infrastructure Renewal - Water9$1,359,019$2,465,000$3,824,019 Safe, Clean Drinking Water1$93,601,600$46,953,900$140,555,500 TOTALS: 22$95,560,619$51,493,900$147,054,519 Summary of Capital Costs (Utility Share) Infrastructure Renewal - Sanitar 4.0% nfrastructure Renewal - Water 4.8% Safe, Clean Drinking Water 91.2% Page1 of THE CITY OF SAINT JOHN 11-Sep-17 SAINT JOHN WATER PROPOSED W & S FUND PROGRAM 2018 MDH: MUNICIPAL DESIGNATED HIGHWAYS PDH: PROVINCIALLY DESIGNATED HIGHWAYS This is a tentative program listing of proposed capital projects. RDH: REGIONALLY DESIGNATED HIGHWAYS w&s: WATER AND SEWER RELATED PROJECTS This list has not been approved by Common Council. G&D: PROJECT IS FOR GROWTH AND DEVELOPMENT Priority assignments are subject to change at any time. *: PROJECTS DEPENDANT ON FUNDING FROM OTHERS Infrastructure Renewal - Sanitary OtherUtility ProjectLocationDescription ShareShare G&D Beach Crescent Lift Millidgeville AreaAnalysis and design for storm sewer separation 045,000 Stationfrom the sanitary sewer at the Beach Crescent lift station, including easement acquisition. Currie AvenuePugsley Avenue to Balfour Line approx. 175 m of 300 mm Concrete 0130,000 sanitary sewer, including design and construction management services. Energy EfficiencyVarious LocationsTechnical analysis regarding energy 075,000 conservation opportunities on various Saint John Water facilities. Glen RoadGlenview Drive to Morgan RoadRenew 215m of existing 200mm Concrete 0210,000 sanitary sewer, including construction management services. Jack's FieldGooderich Street to Wright Line approx. 150 m of 375 mm, 50 m of 300 0190,000 Streetmm and 10 m of 450 mm T.C. Sanitary sewer, including design and construction management services. Leinster StreetSydney Street to Carmarthen Renew approx. 130m of 300mm T.C. with new 0145,000 Street200mm sanitary sewer, including construction management services. Mill StreetAt railroad track crossingLine approx. 28m of 750 mm sanitary sewer 0110,000 under tracks, including design and construction management services. Paddock StreetPaddock Street to Cliff StreetLine approx. 80 m of 375 mm T.C. sanitary 075,000 sewer, including design and construction management services. Rockland RoadParks Street to Cranston AvenueRenew 210 m of 225 mm and 300 mm T.C. 0235,000 sanitary sewers (1891), including design and construction management services. SCADA SystemVarious LocationsDesign, purchase and install the equipment for 600,000350,000 a PLC-5 Migration, Fournier SLC / Panel View Migration, Polymer SLC / Local DTAM HMI Migration at the Millidgeville Wastewater Treatment Facility. Design, purchase and install radio equipment and Twido PLC's at various locations. Project proposed to be partially funded under the Small Communities Fund (SCF). Visart StreetAdelaide Street to Natalie StreetRenew approx. 110m of 225 mm T.C. (1925) 0110,000 with new 200 mm sanitary sewer, including construction management services. Page2 of THE CITY OF SAINT JOHN 11-Sep-17 SAINT JOHN WATER PROPOSED W & S FUND PROGRAM 2018 MDH: MUNICIPAL DESIGNATED HIGHWAYS PDH: PROVINCIALLY DESIGNATED HIGHWAYS This is a tentative program listing of proposed capital projects. RDH: REGIONALLY DESIGNATED HIGHWAYS w&s: WATER AND SEWER RELATED PROJECTS This list has not been approved by Common Council. G&D: PROJECT IS FOR GROWTH AND DEVELOPMENT Priority assignments are subject to change at any time. *: PROJECTS DEPENDANT ON FUNDING FROM OTHERS Infrastructure Renewal - Sanitary OtherUtility ProjectLocationDescription ShareShare Wastewater PumpingCarpenter Place Wastewater Replacement of two pumps with new chopper 0400,000 Pumping Stationstyle pumps, including design and construction management services. $600,000$2,075,000 TOTAL: Page3 of THE CITY OF SAINT JOHN 11-Sep-17 SAINT JOHN WATER PROPOSED W & S FUND PROGRAM 2018 MDH: MUNICIPAL DESIGNATED HIGHWAYS PDH: PROVINCIALLY DESIGNATED HIGHWAYS This is a tentative program listing of proposed capital projects. RDH: REGIONALLY DESIGNATED HIGHWAYS w&s: WATER AND SEWER RELATED PROJECTS This list has not been approved by Common Council. G&D: PROJECT IS FOR GROWTH AND DEVELOPMENT Priority assignments are subject to change at any time. *: PROJECTS DEPENDANT ON FUNDING FROM OTHERS Infrastructure Renewal - Water OtherUtility ProjectLocationDescription ShareShare Glen RoadGlenview Drive to Morgan RoadRenew approx. 210m of existing 200mm 0240,000 watermain, including design and construction management services. Leinster StreetSydney Street to Carmarthen Renew approx. 130m of 200mm C.I. 0150,000 Streetwatermain, including design and construction management services. Loch Lomond WatershedMcBrien and Taylor LakesInvestigate and design the requirements to do 090,000 some civil works at Taylor Lake to invest in further securing the separation of this lake from the watershed and Investigate and design the requirements to fix the damaged control structure at McBrien Lake. Musquash Industrial Musquash Industrial Water Chamber Upgrades and Electromagnetic 050,000 Water SupplySupply Pipeline Engineering Design Musquash Pumping Musquash Pumping StationRelocate substation across the road under the 01,275,000 Station69KV Transmission Line, including design and construction management services. Phase B Ocean Drive Pumping Civic # 103 Ocean DriveInstallation of a back-up power generator at the 0265,000 StationHarbourview Subdivision Ocean Drive Pumping Station, including design and construction management services. Rockland RoadParks Street to Cranston AvenueRenew 210 m of 200 mm C.I. watermain, 0230,000 including design and construction management services. Visart StreetAdelaide Street to Natalie StreetRenew approx. 150m of 200 mm C.I. (1957) 0165,000 watermain, including design and construction management services. * Watermain Cleaning and Various locationsCleaning and lining of existing unlined C.I. 1,359,0190 Lining Phase 15watermains to improve pressure, water quality, and fire flows. Project to be funded under G.T.F. $1,359,019$2,465,000 TOTAL: Page4 of THE CITY OF SAINT JOHN 11-Sep-17 SAINT JOHN WATER PROPOSED W & S FUND PROGRAM 2018 MDH: MUNICIPAL DESIGNATED HIGHWAYS PDH: PROVINCIALLY DESIGNATED HIGHWAYS This is a tentative program listing of proposed capital projects. RDH: REGIONALLY DESIGNATED HIGHWAYS w&s: WATER AND SEWER RELATED PROJECTS This list has not been approved by Common Council. G&D: PROJECT IS FOR GROWTH AND DEVELOPMENT Priority assignments are subject to change at any time. *: PROJECTS DEPENDANT ON FUNDING FROM OTHERS Safe, Clean Drinking Water OtherUtility ProjectLocationDescription ShareShare Safe, Clean Drinking TBDSafe, Clean Drinking Water Program envelope 93,601,60046,953,900 Water Programfor 2018. $93,601,600$46,953,90 0 TOTAL: Page5 of